1.AAC BLOCK WORK (600X200X200)mm or (24X8X8) inch
Manpower required per day for block work (8hrs/day):
AAC BLOCK WORK -8inch- 10 sqm
1 manson
1 male mazdoor
1 female mazdoor
That means 1manson, 1 male mazdoor,1 female mazdoor complete the blockwork 10 sqm in 8hrs.
Example: Calculate the manpower required for to complete the 100 sqm block work (AAC BLOCK WORK (600X200X200)mm in 2 days?
Solution: Qty=100sqm
Duration= 2 days
Per day productivity = 100/2 = 50 sqm
No of mason,male mazdoor,female mazdoor= 50/10=5 nos
No of mason=5(per day)
No of male mazdoor=5(per day)
No. of female mazdoor =5( per day)
To complete the 100 sqm block work= 10 no of manson
=10 no of Male mazdoor
=10 no of female mazdoor
2.AAC BLOCK WORK (600X200X100)mm or (24X8X4) inch and (600X200X150)mm or (24X8X6) inch
Manpower required per day for block work (8hrs/day):
AAC BLOCK WORK -6 and 4inch- 8
1 male mazdoor
1 female mazdoor
That means 1manson, 1 male mazdoor,1 female mazdoor complete the blockwork 8 sqm in 8hrs.
Example: Calculate the manpower required for to complete the 50 sqm block work (AAC BLOCK WORK (600X200X150&100)mm in 2 days?
Solution: Qty=50sqm
Duration= 2 days
Per day productivity = 50/2 = 25 sqm
No of mason,male mazdoor,female mazdoor= 25/8=3.2=3.2 nos
No of mason=3.2(per day)
No of male mazdoor=3.2(per day)
No. of female mazdoor =3.2( per day)
To complete the 50 sqm block work= 6.4=7 no of manson
=6.4=7 no of Male mazdoor
=6.4=7 no of female mazdoor
3.BRICK WORK (190X90X90)mm
Manpower required per day for 9 inch brick work (8hrs/day):
Brick work-9inch- 1.25cum
1 manson
1 male mazdoor
1 female mazdoor
That means 1manson, 1 male mazdoor,1 female mazdoor complete the brickwork 9inch 1.25cum in 8hrs.
Example: Calculate the manpower required for to complete the 20 cum brick work 9inch in 2 days?
Solution: Qty=20cum
Duration= 2 days
Per day productivity = 20/2 = 10 cum
No of mason,male mazdoor,female mazdoor= 10/1.25=8 nos
No of mason=8(per day)
No of male mazdoor=8(per day)
No. of female mazdoor =8( per day)
To complete the 20cum brick work= 16 no of manson
=16 no of Male mazdoor
=16 no of female mazdoor
4.BRICK WORK (190X90X90)mm
Manpower required per day for 4.5 inch brick work (8hrs/day):
Brick work-4.5inch- 5 sqm
1 manson
1 male mazdoor
1 female mazdoor
That means 1manson, 1 male mazdoor,1 female mazdoor complete the brickwork 9inch 5sqm in 8hrs.
Example: Calculate the manpower required for to complete the 150sqm brick work 4.5inch in 2 days?
Solution: Qty=150 sqm
Duration= 2 days
Per day productivity = 150/2 = 75 sqm
No of mason,male mazdoor,female mazdoor= 75/5=15 nos
No of mason=15(per day)
No of male mazdoor=15(per day)
No. of female mazdoor =15( per day)
To complete the 150 sqm brick work= 30 no of manson
=30 no of Male mazdoor
=30 no of female mazdoor