Plastering work- Manpower calculation

 1.Internal Wall plastering:

Manpower required per day for Internal wall plastering (8hrs/day):

Internal wall plastering- 10 sqm

1 manson                

1 male mazdoor 

1 female mazdoor


That means 1manson, 1 male mazdoor,1 female mazdoor complete the Internal wall plastering 10 sqm in 8hrs.


Example: Calculate the manpower required for to complete the 100 sqm Internal wall plastering in 2 days?


Solution: Qty=100sqm

                Duration= 2 days

                Per day productivity = 100/2 = 50 sqm 

                No of mason,male mazdoor,female mazdoor= 50/10=5 nos

                No of mason=5(per day)

                No of male mazdoor=5(per day)

                No. of female mazdoor =5( per day)


To complete the Internal wall plastering work= 10 no of manson

                                                            =10 no of Male mazdoor

                                                            =10 no of female mazdoor


2.External and Ceiling wall plastering:

Manpower required per day for External wall and ceiling plastering (8hrs/day):

Internal wall plastering- 8 sqm

1 manson                

1 male mazdoor 

1 female mazdoor


That means 1manson, 1 male mazdoor,1 female mazdoor complete the External wall and ceiling plastering 8 sqm in 8hrs.


Example: Calculate the manpower required for to complete the 100 sqm External wall plastering and ceiling plastering in 2 days?


Solution: Qty=100sqm

                Duration= 2 days

                Per day productivity = 100/2 = 50 sqm 

                No of mason,male mazdoor,female mazdoor= 50/8=4 nos

                No of mason=4(per day)

                No of male mazdoor=4(per day)

                No. of female mazdoor =4( per day)


To complete the Internal wall plastering work= 8 no of manson

                                                            =8 no of Male mazdoor

                                                            =8 no of female mazdoor